January 2012 |
|
![]() |
Casting done of Non tower slab area.
|
![]() |
Shuttering of Tower A1 for stilt level.
|
![]() |
Column casted at roof level.
|
![]() |
Steel fixing of Tower A2.
|
![]() |
Shuttering work of non-tower area.
|
December 2011 |
|
![]() |
Raft foundation work completed.
|
![]() |
Casting of retaining wall footing completed.
|
![]() |
Layout work above raft foundation.
|
November 2011 |
|
![]() |
Casting of retaining wall In progress.
|
![]() |
Steel binding work in progress.
|
October 2011 |
|
![]() |
Casting of raft foundation in progress.
|
![]() |
Shuttering fixing in retaining wall in progress.
|
September 2011 |
|
![]() |
Steel binding of columns in progress.
|
![]() |
Fixing of shuttering in lift pit in progress.
|
![]() |
Steel fixing in raft foundation in progress.
|
August 2011 |
|
![]() |
Fixing of shuttering in retaining wall in progress.
|
![]() |
Raft foundation steel fixing in progress.
|
![]() |
Steel binding work of retaining wall in progress.
|
July 2011 |
|
![]() |
Steel binding work in progress.
|
![]() |
Steel binding work at foundation raft in progress.
|
![]() |
Brick work in lift pit at tower A2.
|
![]() |
Steel fixing of lift pit at tower A1.
|
June 2011 |
|
![]() |
Removing of soil from PCC.
|
![]() |
Removing of soil.
|
![]() |
Placement of the raw material.
|